02FEB2015 - This is a view of the cleared area (for the beam) looking at the Master Suite. |
02FEB2015 - We planned for the beam when pouring the foundation. This is the rebar sticking out of the slab on the Guest Wing. |
02FEB2015 - This is the rebar sticking out of the patio on the Master Suite. There are only 2 rebars on this side because it was so shallow. |
01MAR2015 - This is Gilbert (Lopez Concrete and Construction) drilling holes for the supporting stakes to be driven in. |
01MAR2015 - Gilbert is checking the lines for the concrete beam. |
01MAR2015 - Gilbert and his worker are tying steel for the beam. |
01MAR2015 - And the rains began.... It was cold and wet. |
03MAR2015 - I used the shop vac to clean the mud and debris out of the forms. It worked pretty good. |
03MAR2015 -Here's a view from inside the courtyard. I'm waiting on the Engineering Inspector to show up now. |
03MAR2015 - I installed 2 layers of drainage through the beam. I didn't want the courtyard becoming a mud pit due to poor drainage. |
13MAR2015 - We needed to remove a tree branch for the concrete truck to back into position. Looks like Gilbert is the one in a bad position here. |
13MAR2015 - The inspection passed and we poured the concrete for the sub grade beam. |
13MAR2015 - Notice how all of the ends of the drainage pipes got covered up. |
13MAR2015 - Here's another view looking into the courtyard. |
25MAR2015 - After the beam was poured... and it rained again... I noticed that their was still a drainage problem in the courtyard and around the front of the beam. |
25MAR2015 - Here's a shot of the water puddling inside the courtyard. This could be a big problem and cause foundation settling. |
25MAR2015 - The french drain is sloped to the base of the beam at the front of the courtyard. |
25MAR2015 - Here's another shot from the front of the house, looking into the courtyard. |
25MAR2015 - I added another layer of silt fabric on top of the french drain system and then covered it with 1.5" rock. |
Here you can see the added layer of silt fabric over the french drain in the courtyard. |
This shows the silt fabric laid over the drain field. |
I then back filled the area with 36 cubic yards of washed sand. |
This is another shot from the front of the house. I brought in additional sand to fill the courtyard to about 2 inches below the patios and covering the black colored waterproofing on the foundation. |